Denver Lock to Salters Lode Lock Crossing
Updated 31/05/2024
We are pleased to inform you that the de-silting works at Denver are now complete ahead
of the original estimate to be completed w/c 27th June.
Our Contractors have now moved on to Salters Lode tidal Lock entrance and have begun
de-silting operations. Works are anticipated to last into mid-June.