More of the Monty takes shape

by

WITH parts of the UK having had their wettest winter since records began in 1836, work on the Crickheath Tramway wharf wall was delayed despite prolonged pumping to reduce water levels.

Volunteers queue with their barrows for some hard graft.

So the main focus of a recent work party was to crack on with lining and blocking just south of the wharf. This section had failed the water testing last October, hence the need for waterproofing, though even here a modest amount of pumping was required before work could start.

Starting to shape the channel.

A further 35 metres of channel were lined and blocked and although there was still work to do above water level, the diggers worked further down the channel in the direction of Schoolhouse Bridge. Following site clearance earlier in the year, it was possible to start the initial profiling of the channel by excavating the bed to the required level (grade) and regularising the bank slopes (profiling).

Article continues below…
Advert

Read Towpath Talk FREE online every month here.

A further 35m of channel lined and blocked to water level. ALL PHOTOS: SUCS


Advert
Get Towpath Talk newspaper delivered every month. Click here to subscribe.

Read Towpath Talk FREE online here.


Sell your boat here.